Estimate Follow-Up Emails & Change Orders: Worked Examples

Updated by the EstimateDynamo team

Follow up on a contractor estimate by confirming receipt, offering to clarify the scope and closing the loop before its actual expiry date. If the work changes, price and document the change separately before revising the total. Use the email examples and $400 change-order breakdown below as starting points, replacing every bracketed field with the real job details.

Before following up, check the estimate

  • Use the same estimate number and revision the customer received.
  • Check the actual validity date and whether your proposed start date is still available.
  • Check for a reply or decline before sending another message.
  • Offer a specific next step: a scope question, site visit or approval discussion. Do not imply work is booked merely because an estimate was sent.

Email 1: confirm receipt

Example timing: two business days after sending, unless the customer agreed a different date. Subject: Did estimate [EST-number] reach you?

Hi [name], I sent estimate [EST-number] for [scope] on [date]. Did it reach you? I can clarify the included work, exclusions or payment schedule. Please reply with any questions, or let me know a convenient time to discuss. Thanks, [your name].

Email 2: help with the decision

Example timing: about a week after sending, if there has been no reply. Subject: Any questions about [project] estimate [EST-number]?

Hi [name], I am checking whether anything in the [project] scope needs explaining. The estimate includes [specific inclusion] and excludes [specific exclusion]. If your priorities or scope have changed, I can prepare a clearly marked revision. Would a short call help? Thanks, [your name].

Mention availability only when it is true, and do not use invented deadlines or discounts to create pressure.

Email 3: close the loop before expiry

Example timing: near the estimate's real expiry date, not automatically day 14. Subject: Closing the loop on estimate [EST-number]

Hi [name], estimate [EST-number] is valid until [date]. If you want to proceed, please contact me so we can confirm the scope, current availability and approval steps. If the project is on hold or you chose another contractor, no problem; let me know and I will close this follow-up. Thanks, [your name].

Stop follow-ups when the customer declines or asks you to stop. An expired estimate may need current supplier costs and a new revision before it can be used.

Handle change orders in writing

When scope changes, record the original estimate reference, the added or removed work, revised quantities, the price difference and any effect on the schedule. Identify who can authorize changes and obtain written approval before extra work begins, subject to the contract and local requirements.

A worked change-order example

Illustrative arithmetic only: an approved original estimate is $4,000 before tax. Extra work adds 4 person-hours at an invented $50 loaded cost per hour ($200) and $120 materials. Included extra costs are $320. A 25% markup adds $80, so the proposed change is $400 and the revised pre-tax estimate is $4,400. The markup gives a 20% margin on the included extra costs; it is not a 25% margin. Include overhead once and use your own costs.

Record the new scope, exclusions, schedule effect, tax treatment and payment milestone next to the $400 change. Keep both the original estimate and the approved revision. This is a pricing example, not a contract form or a statement that a particular approval method is legally sufficient.

Change-order record: what to send for approval

For a reduction, show the removed scope and credit explicitly. Check tax and approval requirements for your contract and jurisdiction. Do not present the illustrative $400 as a standard change-order fee. A sent PDF, an opened email or an app status alone is not evidence of customer approval.

Example record using fictional amounts; not a legal contract form
FieldExample or required detail
Original documentEstimate [EST-number], approved revision [number]
Change referenceCO-01, issue date and customer/project
Added and removed workDescribe measured quantities, materials and exclusions
Extra loaded labor cost4 person-hours x $50 = $200
Extra material cost$120
Included extra cost$320
Markup25% x $320 = $80
Proposed price change+$400 before tax
Revised contract total$4,000 + $400 = $4,400 before tax
Schedule and payment impactState actual date changes and revised milestones
Approval recordAuthorized approver, approval date and retained written record

Deposits and payment schedules

  • Agree any permitted deposit and when it becomes due; check local limits before choosing an amount.
  • Tie progress payments to clearly described milestones.
  • State when final payment is due and how approved changes affect it.
  • Confirm applicable requirements before using late-payment terms.

Keep a record of the version sent

Send the revised PDF or, when available on your plan, a share link. Include the estimate reference and revision date. Keep a separate record of written approval; sending or viewing a link alone does not mean the customer accepted the work.

Put it into practice

Use your own rates, see live totals and download a professional PDF. No account needed.

Create an estimate to send

Frequently asked questions

How many times should I follow up on an estimate?

Two or three polite follow-ups over about two weeks is usually enough. Stop when the customer declines or the estimate expires.

How much deposit should I ask for?

It depends on the job and local rules, since some states limit deposits. Many contractors ask for enough to cover materials. Check your state's requirements.