Electrical work looks simple until a panel is full or a wall is full of old wiring. A repeatable estimating process catches those surprises before you commit to a price.

Inspect before you price

  • Panel size, available slots and amperage
  • Wire type, age and condition
  • Grounding and bonding
  • Access through attics, crawlspaces and finished walls

Count and measure

Count every device, fixture and circuit, then measure each wire run. Lengths drive both material cost and labor time, so a rough guess here is where most underpriced electrical jobs start.

Worked quantity takeoff: 50-foot route

This is a pricing example, not an electrical design. A qualified electrician must determine equipment, capacity, cable or conductor selection, protective devices and local requirements. Measure the actual route, including changes of direction and terminations.

For an illustrative 50-foot route and 10% takeoff allowance, purchase quantity is 50 x 1.10 = 55 linear feet of the specified cable assembly. At an invented $2 per foot, this line costs $110. Measure conduit, fittings and individual conductors separately where required; one foot of route does not necessarily mean one foot of total conductor.

Price labor

Estimate hours per task for the electrician and helper separately. Include setup, testing, labeling and cleanup. Use your loaded hourly cost, not the wage you pay.

Price materials and devices

  • Wire, conduit, boxes and fittings
  • Breakers, panels and subpanels
  • Receptacles, switches and fixtures
  • Consumables and a waste allowance

Add permits and inspection time

Include the permit fee and the time spent on inspections and callbacks. If the customer pulls the permit, say so in writing.

Per-circuit and per-fixture pricing

Many electricians price repeatable work per circuit, per outlet or per fixture. Build those unit prices from your own cost data and check them against your margin each year.

Itemized electrical estimate example

The downloadable PDF uses these same quantities and totals. Replace invented costs with current supplier quotes and loaded labor costs. Include overhead once. A 20% markup is a 16.67% margin on included costs; omitted costs still reduce profit. A helper's time is additional unless explicitly included.

Invented costs for a surveyed EV charger circuit; charger hardware excluded
Included costCalculationAmount
Electrician labor5 person-hours x $100$500.00
Specified cable assembly55 linear feet x $2$110.00
Accessories and devicesIllustrative allowance$200.00
Permit and inspectionIllustrative allowance$120.00
Included cost subtotal$930.00
Markup20% x $930$186.00
Customer price before tax$1,116.00

Make scope and unknowns explicit

  • State whether charger hardware is customer-supplied or included; this sample excludes it.
  • Record the surveyed route, access, specified equipment, testing and labeling, and permit or inspection responsibilities.
  • List panel upgrades, utility work, trenching, concrete cutting and finish repairs as excluded unless itemized.
  • Treat unconfirmed fees as allowances and state how changes are approved. Do not present a permit allowance as a confirmed local fee.
  • Avoid pricing concealed conditions as guaranteed work before the inspection. Use written change approval if the surveyed assumptions change.

Put it into practice

Use your own rates, see live totals and download a professional PDF. No account needed.

Open the electrical estimate calculator

Frequently asked questions

How do you estimate wire and conduit costs?

Measure each run, add slack and waste, and price from a current supplier quote because copper prices change.

Should I charge a diagnostic fee?

Troubleshooting is unpredictable, so many electricians charge a diagnostic fee or hourly rate with a clear minimum.

Keep reading